Don’t Estimate Software Defects

03.11.2014
| 5955 views |
  • submit to reddit

Software Defects = No Estimates

I don’t estimate software defects. Well, I have two exceptions: If I have a backlog of old defects to burn down, I may estimate those. If I have found some new bug that we plan to fix in some later sprint, I may estimate those (though I really don’t like to defer defect fixes). Otherwise, I don’t estimate defects.

Why Not Estimate Software Defects?

Before explaining why, it’s important to pause and consider my context. To get away with not estimating software defects you must have high quality standards, a strong suite of unit tests and a habitual practice of TDD, and you must fix all defects as soon as they are discovered, or at most, 1 sprint later. If that’s not your context, stop reading this and go put TDD into place.

Deciding not to estimate software defects under these conditions is just easier and makes for more conservative release and iteration planning to not estimate defects (or at least not include them in velocity). It’s a simple rule, simple to explain.

Here’s the problem with doing it any other way: If you estimate new defects and include their points in your velocity as you fix them, then you can’t just divide backlog size by velocity to figure out when you’ll be done. By doing this, you are including in your velocity fixed defects but excluding from your backlog the stuff you haven’t found yet. It’s safe to assume you’ll find more defects and so your backlog is growing, whether you recognize that or not. Dividing an inflated velocity number by an underestimated backlog is risky planning. Sure, your burn-up chart may show you a projection of the growth of your backlog and burn-up intercept, but that’s only if you estimate your defects correctly relative to your stories. There’s enough guessing in estimating the rate of growth of your backlog when only considering new story scope increase. Why make it harder by including defects in the computation?

The Challenges of Estimating Software Defects

For sake of example, let’s say we have one new defect each sprint, and let’s assume they are each 1 point on average. Also assume an initial velocity of 10 (without estimating the defects) and backlog of 200 points (without any measure for unknown future defects). If I fix the defect without an estimate, I’ll continue to have a stable velocity of 10 . I’ll have a stable backlog of 200. My math is easy: 200/10=20 sprints. This is easy to teach. And it’s conservative.

The alternative, estimating the defect, gives me a stable velocity of 11 but a backlog that increases by 1 point each sprint. This math is, let’s see, the slope is… uh…. something, and we’ve got the intercept, and, uh… oh I don’t know. We can compute this easily if we know the average defect size and the defect arrival rate, but most teams don’t know their average defect size or defect arrival rate. This is harder to teach. It’s even harder to get people to remember and account for an increasing backlog when they are doing back of the envelope figuring in their head.

Additionally, defects are hard to estimate and the estimates we make for defects often do not reflect the same behavior as for stories – they have a different variance, a different distribution and the mean effort per point is typically significantly different than for stories. Relative estimation between a defect and a story is not the best thing.

Summary

Finally, if an organization finds themselves not ready to start the next release and they’re going to have the otherwise idle teams fix defects until the Product Owner team gets ready, then why estimate the defects?

Similarly for spikes: I tend to not estimate them, and I execute them as quickly as possible.

I lean towards velocity measuring effort put toward Value Delivered, not for defects, rework, or research. I do this because I care greatly about my release commitment/budget. If I inflate my velocity due to defects and spikes (i.e. things that were unplanned) then I’ll end up over-committing to the release: my velocity number will be higher than the actual known value to be delivered.

Let me remind you that there is a lot of context here that is important. If your team has high quality standards and they fix all defects as soon as they find them or perhaps 1 sprint later, then my approach of not estimating works because they do not allow an increasing backlog of defects to accumulate. If, however, your team defers defects, AND intends to fix them later in the release, then my approach is really, really bad poison and you should estimate all your defects and understand the current arrival rate and the historical defect load per release.

I do make exceptions to this rule and I’ve not always held the same belief. An older post on this subject, Estimating Defects – Using Principled Negotiations, discusses what you might do for a myriad of different contexts.

Bottom line: Track, quantify, and represent the effect of software defects separately.